Day 137 – Foundation finished and framing started!

So quite a bit has happened since the last update. I will make an attempt to go through everything that has happened.

As soon as the concrete contractor was done we moved in to start preparing for the concrete floor. This would involve installing interior perimeter drains, conduits for electrical service as well as telephone and cable TV. With this installed we would place some gravel and then top it off with a finer material to provide a smooth surface. On top of this goes a vapour barrier and finally insulation.

Conduits to run cables under the floor slab

We started in the morning with a big pile of white 4″ perforated PVC pipe. This was laid down along the interior of the concrete footings. The purpose of these pipes are to collect any water that might come inside and below the house. For this purpose they have holes along the bottom through which the water might enter. It is not strictly necessary to run perimeter drains on the inside of your foundation. However we made this choice because the ground we sit on it solid and water does not drain through it at all. This way if water does get below the house it will have a way to drain out.

Because we are going with an underground electrical service we need a way to get the main power cable into the house. This can be done either by burying an armoured cable, or providing conduits to pull cables through.
We were very careful in the placement of this conduit as it was supposed to come up right the middle of a wall.
The grey conduit in the picture is for the electrical cable. It is an extra thick type of PVC pipe. Quite expensive and so are the fittings.

Similar requirements exist for the telephone and cable company. In our case we have provided separate conduits for the cable and telephone service. They are the smaller orange pipes.

Unfortunately the contractor placed the sleeves in the concrete in the reverse order, so we had to “snake” the grey and orange pipes around each other rather.
For a quick laugh about the sleeves. I neglected to put couplings on the ends of my conduit sleeves. So when the concrete forms came off everything was flush with the wall as expected only there was no way to slip the couplings over the pipes.
This oversight would require me to chisel out the concrete an inch deep around the three sleeves. After doing about a third of it by hand for an hour I rented a hammerdrill the next day and had it done in 20 minutes.

Willy from Apex Plumbing installing water supply lines

At the same time our plumber came out and started his underslab rough-ins. We put in two waterlines. One that we will use and a spare in case something happens to the first one. They also installed all the sewer lines that will run beneath the floor.

Slinger truck shooting drain rock

With the pipes and conduits in place we called for a truckload of gravel. We used a so-called “slinger truck” which is a truck with a conveyor belt on the rear. Using this conveyor belt the operator can shoot gravel up to 30 feet with high precision. This takes away alot of manual work to get the gravel where it needs to.

Placing gravel wherever needed

We added a minimum of 12″ of gravel throughout the foundation. The gravel serves as a permeable layer that water can flow through, to the drain pipes. It also provides a capillary break, preventing water from wicking up through it as might happen with other, more sandy materials.

Slinging more material in

On top of the gravel we placed a layer of filter fabric. This is to keep the top layer, which will contain a mixture of fine grain particles and gravel from mixing with the gravel, keeping it clean and free draining.
With the fabric laid down we called for the slinger truck again, this time with a load of screened pit run. This is a mixture of gravel and sand with no rocks larger than 2″. When we compact it with a plate compactor it forms a very hard and smooth base for the next stage.

Protected from the rain and ready for insulation

We knew that there was rain in the forecast and we need to keep going to finish the foundation. Because we were about to lay down plastic vapour barrier and insulation it would keep any rainfall from draining out. It would get trapped between the layers and we neede to keep any water out of it.
To this purpose we purchased the largest tarp they had at the store. Trying to wrap exposed concrete walls, with sharp corners, stepped edges and exposed anchor bolts turned out to be a challenge.
With some leftover lumber we screwed together a sort of space frame to hold up the tarp while we worked on the inside. Something that we learned along the way was, if you think you have the tarpe tied down enough, you don’t. If the supports seem sturdy enough, they probably aren’t.
While we were waiting for better weather the tarp came down twice. The day we were hoping to have our floor slab poured we had to spend a whole day tearing up the insulation in sections and vacuuming out standing water trapped on top of the vapour barrier.

The day after that we could finally, after many delays have our floor slab poured. The weather was nice and the truck arrived at 9 o’clock sharp.

Concrete truck getting ready

There was a crew of five. Two guys going back and forth with wheelbarrows moving concrete from the truck to wherever it needed to be while the three others were raking, screeding and checking levels.

Getting there

Crew working hard

Control joint

Getting the concrete in took about 3 hours. Then half of the crew left and the two remainding members used machines to finish the floor. I did not get any pictures of them as I had left at this point.

Concrete truck leaving

That will be the last we see of the concrete truck until it is time to build the carport.

With the concrete setting I was ready to inform the people I have hired for the assembly work that they could get started.
I was very careful in picking who we used for this part and we ended up with someone who has done quite a bit of work out on Ship’s Point.

The floor slab was poured on Tuesday Jan 31st and they started the very next day.

Framing the prefab interior walls

By the time I arrived at around lunchtime, they had removed the rickety tarp supports and were moving the lower floor wall panels in place.

Framing the prefab interior walls

The North side with the bedroom window opening at the stepped concrete wall.

The angled piece is the wall in the stairwell.

Bedroom window

The bedroom window is an example of what might happen if, during the review process of the prefab drawings, you mistake your wording.
During the design you need to check all the drawings against each other to make sure that everything lines up properly. In this case it involves the architectural drawings that the dimension of the foundation derive from. On top of that I need to reconcile them with drawings from Insulspan as well as Pacific Building Systems. In this case I noted that the “bottom of sill” of the wall panel framing the window be at 4’9-1/2″ to concide with a concrete wall of 4′-8″ with a 1 1/2″ sill plate sitting on it. But I said “bottom of sill”, when it should have said “TOP of sill”. This means the wall panel window starts 1 1/2″ higher than the wall. It is no big deal to add some extra wood afterwards to bring everything in line, but it is added work and materials that should not have been there and it highlights the importance of drawing review and terminology.

Preparing the prefabbed wall panels

The wall panels come complete with pressure treated sill plates. The guys added extra sill gasket to the bottom of the walls. Not strictly necessary, but good for the longevity and a nice touch.

The front wall will be made from SIPs panels that tie into the floor system. The easiest way to deal with his is to temporarily brace the framing until the SIPs get installed.

Floor sheathing going in

At the end of Friday they had installed all the lower floor walls, the floor joists and started on the sheathing.

Pink floor joists and LVL boards

The joists are pink because they are painted with a coating that is mold and fire resistant.

Framing details

As the walls start going up we can start getting a sense of the rooms.

View from bedroom

Temporary supports

This is where we are sitting now. On Monday they will work as far as they can go before things need to start to tie in with the SIPs panels, which are scheduled to arrive on Tuesday.

Posted in Uncategorized | Leave a comment

Not much happening at the moment

With the snow all the work has stopped and we are just waiting for things to warm up a little so we can continue.

In the mean time, have some pictures from the surrounding area.

Park at the end of the road

Looking towards Denman Island

Some of the neighbours

The local wharf

More neighbours

 

Posted in Uncategorized | Leave a comment

Day 105 – Still working on the foundation

So we have concrete walls poured!

After we had our footings poured we expected the rest of the foundation to move along quickly. However the contractor we had hired decided to disappear. We attempted communication for a week, but he did not even return our phone calls.
At that point we decided to find someone else. After calling around for recommendations we talked to a new contractor who could get to work right after Christmas.

The new contractor started work on Dec 28th, worked until the 30th and resumed on January 2nd. I have to give him credit for working through the pounding rain. I was miserable just receiving a truck for a couple of hours in it. He poured the concrete on Friday Jan 6th.
I wanted to be there to take some pictures but he forgot to call me.
27 yards of concrete and 3 hours on a pumptruck later we finally have our foundation walls.

He left the forms in over the weekend and started to strip the the next Monday which took a couple of days.

Then we started to prepare all the work that happens before the floor slab goes in, interior perimeter drain, sewer runs and service ducts.
The plan was to lay out our pipes and ducts, then call for an inspection.
After that we fill with 3/4″ drainrock to the top of the footings, cover with fabric and then 2″ of compacted sand, lay down vapor barrier and finally 2″ of extruded polystyrene insulation.

Then it’s time to call another contractor who will place and finish the 4″ floor slab.

In the mean time we have a pile of precut joists and beams and prefabbed interior walls waiting to be assembled.

Starting on the formwork

The contractor working on his forms

Building up the wall forms, piece by piece

Poured foundation walls

Bracing the forms and working platforms

A view on the inside. Lots of bracing to hold the 10+ foot walls.

Prefabbed interior walls and floor joists. Wrapped up for protection from the elements.

Posted in Uncategorized | Leave a comment

Day 81 – Meter Pole Installation

Early in the process we decided to use underground services for two reasons. Practical and esthetical. The practical reason is we avoid having to hang overhead wires through dense foliage, in the inevitable winter storm we minmize the chance of branches falling on the wires. It will still happen, but we cut down on the chance of it happening. The esthetic part is we get to keep a nice and clean roof line without an unsightly weatherhead hanging on the house.

To have the meter pole installed we called a local contractor called Addy Power pretty early on and got a quote. They seem to be the only game in town but the price was good. It took many phone calls to get their attention but once they gave me a date for the work it was done right away.

This is what I was met with when I arrived in the morning, a big red truck with a big auger on the end of a boom. The guys had already started to drill the hole for the pole.

Augering out hole for the meter poleAfter the hole was dug they cleaned off the auger, retracted it onto the boom and hoisted up the 25 foot meter pole.

25' pole with meter baseA very large part of the pole sits underground, compare the two photos.

Placed in holeThe view from the road. This was the last I saw of the work as I had to make my way into the office.

View from road

Posted in House Building | Leave a comment

Day 69 – Footings are poured

After several delays the concrete contractor finally got our footings poured.  The contractor delayed the inspection more than once and on one occasion I went to meet the building inspector at the lot and nothing at all had happened.
When I arrived the day of the pour was already a concrete- and a pump-truck waiting,  Graeme from Mayco gave us a good price on the concrete. The guys got to work quickly to pour the concrete.
The pour itself went very quickly, and before we knew it it was done and everyone had left. The whole thing didn’t take longer than a couple of hours.

Cutting rebar

Pump truck standing by

Pouring footings

Wet placing of rebar into footings

Some left over concrete being turned into stairs

We've got footings!

Posted in House Building | Leave a comment

Day 31 – More digging and cutting of some trees

Today the arborist came out and took care of the trees for us.
We decided to take out the Maple tree as it would be too close to the construction. Hopefully it can be processed and reused for something around the interior of the house

In the rear corner of the backyard sat a fairly large, dead cedar tree. Instead of cutting it down we decided to turn it into a “wildlife” tree. It entails cutting the top of to remove any danger it might pose and more of less just leaving it for birds and insects to move it.

This will be the backyard. You just need to imagine it with grass instead of mud.

On top of this we also topped and limbed a leaning Douglas Fir to remove any hazard it might post in the next storm.

After all this was done we got back to digging!
About 3 feet or so down into the ground we hit some fairly hard shale. The machine can break it apart easily depending on the angle you can get at it. It just takes a bit longer to get to the preferred depth.
We have marked the level we want to be on with green spray paint.

We also have a new construction driveway. We used the excavator to strip of the top 12″ of the soil and then proceeded to spread about 40 tons of pit run to prepare a driveway for the large delivery trucks which will be arriving within a few weeks.

Gratuitous excavator shot.

Posted in House Building | Leave a comment

Day 21 – Excavation

We finally got a chance to start the excavation today. We were originally slated to start a couple of days previous but delivery problems kept the machine from the lot until today. We missed a few beautiful sunny days and the rain was pouring the whole morning.

First thing we did was to tackle the old foundation. We dug around the walls and then just grabbed the concrete and pulled straight up. At first it seemed like it would fail again, but after some groaning the concrete let go in a thinner spot and snapped. After that it was much easier to get some leverage and break it apart piece by piece. Later on we will have to break it down further and dispose of in some way.

Demolishing the old foundation

Breaking it up into smaller pieces

All piled up.

With the old foundation out we were able to start the layout of the excavation. Before today I created an excavation plan, this was a version of the site plan with only the contours of the excavation showing. The plan also featured a few reference points and distances to all the corners from these points. This made the layout work relatively fast and easy.

Excavation layout


One problem with excavation is figuring out what do you with the surplus dirt. I put out an ad on craigslist advertising “free fill”. I found a property owner just five minutes away who wanted it and arranged to have it trucked away. This solved our problem and saved us some on trucking. To make sure we do not dig too deep we have rented a laser level. The level works in conjunction with a pole-mounted transponder. You calculate the depth you need from the head of the laser and place the transponded at the appropriate height. With this you can very simply place the pole at the bottom of the hole and know if you need to go down further. It is very important not to dig down further than you need.
With everything prepared we were able to put a shovel to the ground.

Breaking ground

Piling the dirt between the truck loads

Laser level

Digging deeper

A house-shaped hole

Dumptruck arriving for another load

End of day 21

And that is the end of todays work. We will be continuing next week.

Posted in House Building | 1 Comment

Day 1 – Clearing the land

Day 1

The plan for the day was to get most of the clearing done. We have rented a small Bobcat excavator and when we arrived in the morning it was waiting for us at the bottom of the lot. My brother-in-law will be operating the machine today. He’ll be much more efficient than I could hope to be.

The excavator makes quick work of the shrub, small firs and alders

About where the excavator is shown is where our rear deck will be.

The tools of the trade.

The old foundation proved tougher than expected. We’ll deal with it on the first day of excavation with a much larger machine. The small Bobcat couldn’t even budge it.

Old Hemlock log too heavy for the machine to move in one go. A couple of bucks with the chain saw makes it easier to move. Still a bit heavy though.

Not bad for a days work.

Posted in House Building | Leave a comment

The lot, untouched

This is what the lot looks like now, before we have taken various pieces of heavy machinery to it. It won’t stay this way much longer.

Posted in House Building | Leave a comment

Site Plan

We knew from the start that we did not want to bulldoze the lot and place the house wherever convenient. There are quite a few mature Cedar and Fir trees and we want to keep whatever we can. The placement of the house and accessory structures is decided mostly by the location of these larger trees.

Early in the process we decided to go for a “storey-and-a-half” design. Essentially a main floor half embedded in the ground as a walkout-basement and an upper floor. This will allow us to double our square footage without doubling our price. With the slope very well suited for this it was an easy decision to make.

The lower floor will contain the bedrooms and has a dedicated patio area serving the two main bedrooms.

The upper floor will have a nice sized deck as well as an enclosed porch. The main floor backs onto a lawn area which will be flattened and retained to make it level.

The house will have  a detached 2-car carport. We do not want an enclosed garage but have opted for a nice carport instead. There will be a small workspace and storage in an enclosed area in the rear of it.

Our zoning allows for a secondary suite, so we have a location planned for the future. We do not know when we will build it, but we are planning and providing early for it.  For this purpose we also had to allow enough room behind the house to allow equipment to move in the future.

Posted in House Building | Tagged , , , | Leave a comment