Monthly Archives: December 2011
Day 81 – Meter Pole Installation
Early in the process we decided to use underground services for two reasons. Practical and esthetical. The practical reason is we avoid having to hang overhead wires through dense foliage, in the inevitable winter storm we minmize the chance of … Continue reading
Posted in House Building
Leave a comment
Day 69 – Footings are poured
After several delays the concrete contractor finally got our footings poured. The contractor delayed the inspection more than once and on one occasion I went to meet the building inspector at the lot and nothing at all had happened. When … Continue reading
Posted in House Building
Leave a comment